Enka Insaat Ve Sanayi A.S. ("Enka" or the "Respondent") v OOO Insurance Company Chubb ("Chubb" or the "Appellant") - UK Supreme Court Hearing Report (July 2020)

L. Winnington-Ingram
Winnington-Ingram, Lucy
E. Litina
Litina, Eva

Article from: TDM 3 (2021), in Case Comments & Awards

Background to the Dispute

This dispute has its genesis in the contractual arrangements for Enka's participation in building the Berezovskaya power plant in Russia for PJSC Unipro (then called E.ON Russian) ("Unipro") pursuant to a contract entered into with Unipro's general contractor, CJSC Energoproekt (the "Contract"). Pursuant to the Contract, Enka was to provide works relating to the boiler and auxiliary equipment installation. Energoproekt's subsequently assigned its rights under the Contract to Unipro. Unipro was insured by Chubb Russia under a primary policy, with reinsurance and retrocession ...

To read this article you need to be a subscriber

Sign in

Forgot password?

Sign in

Subscribe

Fill in the registration form and answer a few simple questions to receive a quote.

Subscribe now

Why subscribe?

TDM journal

Access to TDM Journal articles (well over 2500 articles in total for Premium account holders)

Legal & regulatory

Access to Legal & Regulatory data (well over 10000 documents)

OGEMID

OGEMID membership (lively discussion platform bringing together the world's international dispute management community)

Suggested Citation

L. Winnington-Ingram; E. Litina; "Enka Insaat Ve Sanayi A.S. ("Enka" or the "Respondent") v OOO Insurance Company Chubb ("Chubb" or the "Appellant") - UK Supreme Court Hearing Report (July 2020)"
TDM 3 (2021), www.transnational-dispute-management.com

URL: www.transnational-dispute-management.com/article.asp?key=2817