Smith Cogeneration Bangladesh PVT LTD v Bangladesh Power Development Board and The Government of Bangladesh - ICC International Court of Arbitration Case No 10372-OL-ESR-MS - Final Award - Damages and Costs - 30 October 2003

Country
Year

2003

Summary

...

DECISION:

84. Smith has established its claim against the Board for lost profits, lost development costs and lost fees in the sum of $10.42 million.

85. The Tribunal orders that the Board shall pay costs of the arbitration assessed by the ICC at $625,000 and the sum of $516,567 towards the legal costs and disbursements incurred by Smith.

86. The Tribunal further orders that simple interest shall be paid on the damages and costs awarded in favour of Smith. Interest shall run at the rate of 4%, beginning on the dates indicated above at paragraph 82 until such time as the relevant principal sum is paid.

...

John Tackaberry Q.C.
Ajmalul Hossain Q.C.
Arthur Marriott Q.C

To download this document you need to be a subscriber

Sign in

Forgot password?

Sign in

Subscribe

Fill in the registration form and answer a few simple questions to receive a quote.

Subscribe now

Documents missing? Documents to share? Let us know!

If you know of documents which are currently missing from our Legal & Regulatory database do let us know. You can send them directly to us for inclusion in the database, anonymously or otherwise.
Learn more here